Progress Photos
Progress Photos

Project site 05-24-22-7 Masons continue to lay up bearing walls to receive precast topping - 2nd floor in area B along with laying up stairways in areas C and B. Electricians continue underground conduit in area D and area C. Plumbers are installing underground plumbing in area C and B. Finishing area D last week. Post D excavation is installing drainage rock in area D.

press to zoom
Progress photos
Progress photos

Project site 03-15-22-1

press to zoom
Progress photos
Progress photos

Project site 03-15-22-2

press to zoom
1/29